CENTREWAY ARCADE REMEDIATION, CAMBRIDGE

Category
COMPLETED 2018, QUANTITY SURVEYING, WAIKATO, WEATHER TIGHTNESS REMEDIATION

Remedial works at Centreway Arcade included a full re-roof including new internal gutters, new cladding to east and west shop front elevations, new gutters and membranes to decks and new aluminium joinery. While the majority of the remedial works were carried out, the building was fully wrapped using a large scaffolding structure. Centreway Arcade is a three storey building constructed during the 1980’s with retail tenancies at ground level. The building includes an internal public through-access between Victoria St and Empire St. First and Second floors include a Yoga studio and offices.

Total Value: $1.2 million

ECS Services: Project QS services

Completion date: 2018

Project Duration: 9 months

Client: Body Corporate 32897

Main Contractor: Foster Maintain

Architect: Babbage Consultants

Structural: BTW